PRINCE2 Foundation — Question 150

Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?

Answer options

Correct answer: B

Explanation

The correct answer is B, as a cross-functional project involves multiple stakeholders with differing roles and motivations, which leads to varied perspectives. Options A, C, and D do not specifically address the diversity of viewpoints and motivations among different parties involved in the project.