PRINCE2 Foundation — Question 150
Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?
Answer options
- A. Change
- B. Cross-functional
- C. Unique
- D. Risk
Correct answer: B
Explanation
The correct answer is B, as a cross-functional project involves multiple stakeholders with differing roles and motivations, which leads to varied perspectives. Options A, C, and D do not specifically address the diversity of viewpoints and motivations among different parties involved in the project.