PRINCE2 Foundation — Question 137
Which management product is the team manager role responsible for producing?
Answer options
- A. Stage plan
- B. Checkpoint report
- C. Project product descriptions
- D. Highlight report
Correct answer: B
Explanation
The correct answer is B, as the team manager is specifically tasked with creating the Checkpoint report to communicate progress and issues. The other options, such as the Stage plan and Highlight report, are not the direct responsibility of the team manager, and Project product descriptions are usually created earlier in the project lifecycle.