PRINCE2 Foundation — Question 138

In which process is the PID reviewed and, if necessary, updated to reflect external factors that may affect the delivery and business justification of the project?

Answer options

Correct answer: D

Explanation

The correct answer is D because managing a stage boundary involves reviewing the PID to ensure it aligns with any changes in the project environment. The other options either focus on initial project setup or ongoing management without specifically addressing the need to update the PID based on external factors.