PRINCE2 Foundation — Question 136
In which process does the project manager monitor the work assigned to a team manager?
Answer options
- A. Controlling a stage
- B. Directing a project
- C. Managing a stage boundary
- D. Managing product delivery
Correct answer: A
Explanation
The correct answer is A, as 'Controlling a stage' involves monitoring the progress of the work being carried out by team managers. The other options, such as 'Directing a project' and 'Managing product delivery', focus on broader project leadership and deliverables rather than the specific oversight of tasks within a stage.