PRINCE2 Foundation — Question 121
From which perspective does the 'managing product delivery' process view the project?
Answer options
- A. Corporate, programme management or the customer
- B. Project board
- C. Project manager
- D. Team manager
Correct answer: D
Explanation
The 'managing product delivery' process is primarily focused on the perspective of the Team manager, who is responsible for overseeing the day-to-day activities and ensuring that the team delivers the products as intended. The other options represent higher-level viewpoints, such as corporate or programme management, which do not directly engage with the execution of product delivery.