PRINCE2 Foundation — Question 120
How should a risky and complex project be planned in order to meet the minimum requirements for applying the 'plans' theme?
Answer options
- A. A specific plan must be produced for managing agreed risk responses
- B. The project manager must consider having more management stages
- C. The defined tolerances must be aligned to the project board's risk attitude
- D. A diagram showing the product interdependencies must be produced
Correct answer: D
Explanation
Option D is correct because producing a diagram that illustrates product interdependencies is essential for understanding the project's structure and managing complexities. The other options, while relevant to risk management and project governance, do not directly address the fundamental planning requirement of visualizing how project components relate to each other.