PRINCE2 Foundation — Question 122
Which process has the objective of ensuring that everyone understands who is to be involved in the project's decision making?
Answer options
- A. Starting up a project
- B. Directing a project
- C. Initiating a project
- D. Controlling a stage
Correct answer: C
Explanation
The correct answer is C, as initiating a project involves defining the project and determining who will participate in decision-making. Options A and B relate to project inception and management but do not specifically address the decision-making roles. Option D pertains to overseeing a specific phase of the project, not the overall decision-making process.