PRINCE2 Agile Foundation — Question 19
During which process should release planning be done for the FIRST time?
Answer options
- A. Initiating a project
- B. Managing a stage boundary
- C. Managing product delivery
- D. Controlling a stage
Correct answer: A
Explanation
The correct answer is A, as release planning is typically established during the initiation of a project to set expectations and outline the deliverables. Options B, C, and D refer to processes that occur after the project has been initiated, where the focus is more on execution and management rather than initial planning.