PRINCE2 Agile Foundation — Question 20

Which is typically used in agile when estimating detailed requirements during sprint planning?

Answer options

Correct answer: D

Explanation

T-shirt sizing is a popular technique in agile for estimating work by categorizing tasks into sizes, which helps teams gauge the effort involved. The other options, such as Rationalism, Trading, and Visioning, do not specifically pertain to the estimation of detailed requirements in the context of sprint planning.