PRINCE2 Agile Foundation — Question 18
How does agile address the risk associated with the project not being fully understood at the beginning?
Answer options
- A. By allowing a lot of detail at the start
- B. By avoiding too much detail at the start
- C. By requiring details at the start
- D. By preventing the analysis of details at the start
Correct answer: B
Explanation
The correct answer is B because agile methodologies focus on flexibility and adaptability, allowing teams to avoid excessive detail at the beginning to better respond to changes and uncertainties. Options A and C suggest a need for detailed planning upfront, which contradicts the agile principle of iterative development. Option D implies a complete halt on detail analysis, which is not aligned with agile practices.