Project Management Professional (PMP) — Question 959

A struggling company is executing a critical project. However, due to external environment changes, there is not enough funding to complete the project.

What should the project manager do first?

Answer options

Correct answer: D

Explanation

The correct choice is D because assessing the impact and evaluating alternatives allows the project manager to understand the situation better and explore feasible options. Reducing the scope (A) might not address the core issues, parking the project (B) halts progress, and asking for more funding (C) might not be viable without understanding the project’s options first.