Project Management Professional (PMP) — Question 958
A project manager has been working on a critical project to transform an organization's operations. The project manager had successfully completed four sprints when the innovation director was replaced. The new director placed a hold on the project until a new strategy can be put in place.
What should the project manager do first?
Answer options
- A. Discuss the vision and possible impacts with the new director.
- B. Review the risk management plan from previous projects with the new director.
- C. Escalate to the project sponsor to remove the project hold.
- D. Seek approval from the new director to replace the current contingency budget.
Correct answer: A
Explanation
The correct answer is A because discussing the vision and potential impacts with the new director is crucial to align on the project's direction and gain support. Option B, while reviewing risks is important, should come after establishing a clear vision. Escalating to the project sponsor (C) or seeking budget changes (D) without first understanding the new director's perspective may lead to further complications.