Project Management Professional (PMP) — Question 958

A project manager has been working on a critical project to transform an organization's operations. The project manager had successfully completed four sprints when the innovation director was replaced. The new director placed a hold on the project until a new strategy can be put in place.

What should the project manager do first?

Answer options

Correct answer: A

Explanation

The correct answer is A because discussing the vision and potential impacts with the new director is crucial to align on the project's direction and gain support. Option B, while reviewing risks is important, should come after establishing a clear vision. Escalating to the project sponsor (C) or seeking budget changes (D) without first understanding the new director's perspective may lead to further complications.