Project Management Professional (PMP) — Question 957

A project manager notices the team is disagreeing on the level of effort required to complete a task. What should the project manager do?

Answer options

Correct answer: C

Explanation

The correct answer is C because facilitating a discussion where each member explains their estimates promotes understanding and helps the team reach a consensus. Option A is not effective as averages can mask individual insights, while B allows for indefinite delays and D removes team input, undermining collaboration.