Project Management Professional (PMP) — Question 957
A project manager notices the team is disagreeing on the level of effort required to complete a task. What should the project manager do?
Answer options
- A. Advise the team that an average of all the estimates will be used as it will be the most reliable level of effort.
- B. Advise the team that they can resolve the estimation issue and they can work on it as long as it takes.
- C. Advise each team member to explain the rationale for their estimate and then ask the team to come to consensus.
- D. Advise the team that the project manager will determine the level of effort since the team cannot agree.
Correct answer: C
Explanation
The correct answer is C because facilitating a discussion where each member explains their estimates promotes understanding and helps the team reach a consensus. Option A is not effective as averages can mask individual insights, while B allows for indefinite delays and D removes team input, undermining collaboration.