Project Management Professional (PMP) — Question 942

A project team member does not submit the project status report on time. The team member is frustrated about being required to complete the report. The team member believes that the report does not reflect the reality of the project, has too many pages, and will not be read by stakeholders.

What should the project manager do?

Answer options

Correct answer: A

Explanation

The correct answer is A because reviewing the requirements with the team member can help clarify the report's purpose and address their frustrations, potentially improving future submissions. Option B does not address the root cause of the issue, while C may not resolve the underlying problem with the team member's attitude towards the report. Option D escalates the issue without attempting to resolve it collaboratively.