Project Management Professional (PMP) — Question 941
A project manager has been assigned to take over an existing software project. The project manager inherited a lean team comprised of key stakeholders, subject matter experts (SMEs), and senior developers. While reviewing the project status with the team, the project manager observes that the team seems to lack direction and enthusiasm.
What should the new project manager do?
Answer options
- A. Encourage participation in decision making and empower the team.
- B. Ensure everyone performs their assigned tasks as planned.
- C. Meet with the project sponsor and propose a corrective action for the project.
- D. Organize frequent team building sessions and update the risk register.
Correct answer: A
Explanation
The correct answer is A because encouraging participation in decision-making and empowering the team can foster a sense of ownership and motivation, which is essential in revitalizing a disengaged team. Options B, C, and D focus more on task management or external actions instead of directly addressing the team's lack of enthusiasm and direction.