Project Management Professional (PMP) — Question 940

The project manager's firm is executing a construction project. The project is stalled due to reemerging conflicts and misunderstandings among stakeholders.

What should the project manager do to ensure a smooth start and completion of the project?

Answer options

Correct answer: D

Explanation

The correct answer is D because identifying the root cause of misunderstandings is crucial for resolving conflicts and ensuring all parties are aligned. Option A, while collaborative, does not focus on resolving the underlying issues. Option B suggests canceling the project, which is not a constructive solution. Option C may lead to further complications if misunderstandings are not addressed before project initiation.