Project Management Professional (PMP) — Question 936
A project manager has been assigned to a hybrid project. The project manager needs to ensure all team members are collaborating and are aware of the project's ongoing changes.
What should the project manager do?
Answer options
- A. Encourage collaboration on a daily basis, facilitating different communication channels.
- B. Distribute a project newsletter that includes any project changes and required project information.
- C. Meet daily with the project team and include a monthly report on the risks and issues.
- D. Send out daily emails with the project status and task lists to all team members.
Correct answer: A
Explanation
The correct answer is A because encouraging daily collaboration fosters open communication and ensures that team members are in sync with the project's developments. Option B, while informative, may not facilitate real-time collaboration. Option C focuses more on reporting rather than collaboration, and option D relies on emails, which may not promote interactive engagement among team members.