Project Management Professional (PMP) — Question 936

A project manager has been assigned to a hybrid project. The project manager needs to ensure all team members are collaborating and are aware of the project's ongoing changes.

What should the project manager do?

Answer options

Correct answer: A

Explanation

The correct answer is A because encouraging daily collaboration fosters open communication and ensures that team members are in sync with the project's developments. Option B, while informative, may not facilitate real-time collaboration. Option C focuses more on reporting rather than collaboration, and option D relies on emails, which may not promote interactive engagement among team members.