Project Management Professional (PMP) — Question 935
An agile team has been assigned to a project that mandates the implementation of changes to key government products. The team has been given 6 months to fulfill this mandate.
What should the team lead do next?
Answer options
- A. Create the project charter and statement of work (SOW) to estimate the changes and the scope of the change.
- B. Create all of the stories just for the next sprint and skip the epics until the next sprint.
- C. Create all of the stories needed to fulfill this change, document them in the backlog, and prioritize them according to business value.
- D. Create the epics at a high level for the requirements and begin grooming sessions.
Correct answer: D
Explanation
The correct answer is D because creating high-level epics helps in understanding the overall requirements and allows for effective planning and prioritization. Options A and B are too focused on immediate tasks instead of the broader vision, while C does not consider the high-level organization of work that epics provide.