Project Management Professional (PMP) — Question 937

A project leader is assigned to a new project and is asked to assemble an effective five-member agile team. If the project leader has no restrictions, which team should they choose?

Answer options

Correct answer: A

Explanation

The correct choice is A because having team members with general skills who can collaborate enhances flexibility and adaptability, which are essential in agile methodologies. Options B and C emphasize individual expertise and independence, which can hinder collaboration, while D focuses on geographical dispersion that may complicate communication and teamwork.