Project Management Professional (PMP) — Question 933
During a project to develop a new pharmaceutical product, the project manager was informed that there has been a change in government regulations regarding the materials of the project. What should the project manager do?
Answer options
- A. Update the contingency plan to take this issue into account.
- B. Meet with the stakeholders to update the risk register and risk management plan.
- C. Study the new regulations with the team and evaluate if there is any impact on the project variables.
- D. Review the procurement documentation and modify requirements as needed.
Correct answer: C
Explanation
The correct answer is C because it is crucial for the project manager to thoroughly understand the new regulations and their implications on the project's scope, timeline, and resources. Options A, B, and D, while important, do not directly address the immediate need to assess how the regulatory changes will impact the project's execution and deliverables.