Project Management Professional (PMP) — Question 931

An IT company's office is closed abruptly due to a new government restriction. All employees are now working remotely. Project team A has a critical project delivery due in 2 weeks. The project manager, apprehensive about this sudden change, instantly emails the customer explaining that the project delivery will be delayed. The customer is unhappy with this and has escalated the issue to senior management.

What should the project manager have done differently?

Answer options

Correct answer: C

Explanation

The correct approach would have been to assess the situation with project stakeholders first and communicate the impact to the customer (option C). This would allow for a more informed discussion about the delay. The other options either involve premature communication to senior management or fail to provide the customer with a comprehensive understanding of the situation.