Project Management Professional (PMP) — Question 921
A complex project is in the execution phase. A key stakeholder who is new to the project has not been approving project deliverables, which could impact the overall progress.
What should the project manager do next?
Answer options
- A. Capture this in the issue log and escalate it to the project sponsor.
- B. Discuss the need to influence this stakeholder with the sponsor.
- C. Meet with the stakeholder to understand what is causing the delays.
- D. Facilitate a brainstorming session to find potential workarounds.
Correct answer: C
Explanation
The correct answer is C because meeting with the stakeholder allows the project manager to directly understand the reasons behind the approval delays, which is crucial for addressing any issues. Options A and B focus on escalating the situation without first trying to resolve it directly, while D suggests a brainstorming session that may be premature without first understanding the stakeholder's concerns.