Project Management Professional (PMP) — Question 921

A complex project is in the execution phase. A key stakeholder who is new to the project has not been approving project deliverables, which could impact the overall progress.

What should the project manager do next?

Answer options

Correct answer: C

Explanation

The correct answer is C because meeting with the stakeholder allows the project manager to directly understand the reasons behind the approval delays, which is crucial for addressing any issues. Options A and B focus on escalating the situation without first trying to resolve it directly, while D suggests a brainstorming session that may be premature without first understanding the stakeholder's concerns.