Project Management Professional (PMP) — Question 920
A junior project manager was recently hired to lead a complex project scheduled to kick off in 2 weeks. The junior project manager was introduced to another project manager for mentoring.
Which two benefits will the junior project manager realize by being assigned to a mentor? (Choose two.)
Answer options
- A. The mentor will be involved in the decision-making processes implemented by the junior project manager.
- B. The mentor can provide past project documentation with early warning indicators that potential problems could occur.
- C. The mentor will be immediately available to take over the project if there are problems or project delays.
- D. The junior project manager reports administratively to their mentor so that human resource (HR) questions can be answered quickly.
- E. The junior project manager can discuss certain problems with their mentor without fear of retribution.
Correct answer: B, E
Explanation
The correct answers, B and E, highlight the mentor's ability to provide valuable insights from past experiences and create a safe space for discussion. Options A and C incorrectly suggest that the mentor will take over decision-making or control of the project, which is not the primary role of a mentor. Option D misrepresents the reporting structure, as mentoring does not typically involve direct administrative oversight.