During regular project progress review meetings, one team member shares bad news that has a significant impact on the project schedule. How should the project manager react to ensure the project remains successful?

Answer options

Correct answer: C

Explanation

The correct approach is to focus on recovery and ways to get back on track, as this encourages problem-solving and teamwork. Simply logging the issue or punishing the team member can create a negative environment and hinder progress. Highlighting the criticality of the situation without actionable solutions may lead to panic without direction.