Project Management Professional (PMP) — Question 92
A new regulation has been approved that will impact the deliverables in the fourth phase of the project. The delivery is following an iterative approach and is currently completing the second phase.
What should the project manager do next?
Answer options
- A. Consult with the project sponsor to discuss a cost increase
- B. Acquire approval for an exception to the implementation of the new regulation
- C. Get approval for the additional budget from the steering committee
- D. Meet with subject matter experts (SMEs) to access the impact to objectives
Correct answer: D
Explanation
The correct answer is D because meeting with SMEs will provide insight into how the new regulation affects project objectives, allowing the project manager to make informed decisions. Options A, B, and C focus on budget and approval processes rather than assessing the immediate impact of the regulation, which is crucial at this stage.