Project Management Professional (PMP) — Question 91
A marketing team is developing ideas in order to revamp an existing product. The marketing executive reaches out to the project manager to make sure that necessary measures are in place for a successful launch.
On what should the project manager focus?
Answer options
- A. Ensuring that the team is also focused on the overall change management plan
- B. Determining and aligning performance indicators that will help in assessing successful delivery
- C. Planning for regular project updates to cover the status of critical deliverables
- D. Ensuring that the scope management plan is in place to cover all related objectives
Correct answer: B
Explanation
The correct answer is B because aligning performance indicators is crucial for measuring the success of the project upon delivery. While options A, C, and D are important, they do not directly address the need for specific metrics that assess success, which is the primary focus for the project manager in this context.