Project Management Professional (PMP) — Question 93

A healthcare organization hired a new compliance specialist to ensure that the healthcare compliance needs are met. The feedback about the new compliance specialist from the team was average.
What should the project manager do to help the new compliance specialist improve?

Answer options

Correct answer: A

Explanation

The correct answer is A because a one-on-one meeting allows the project manager to directly understand the specialist's challenges and provide tailored support. Options B and D involve escalating issues rather than directly assisting the specialist, while option C may not address specific areas needing improvement.