Project Management Professional (PMP) — Question 908
A project team delivered a critical deliverable to the customer. The customer complained that the maintenance manual was not included.
What should the project manager do next?
Answer options
- A. Review the terms and conditions of the contract.
- B. Submit a change request to include the manual.
- C. Review the stakeholder engagement plan.
- D. Add the needed manual and update the risk log.
Correct answer: A
Explanation
The correct answer is A because reviewing the terms and conditions of the contract is essential to determine whether the maintenance manual was a contractual obligation. Options B, C, and D do not address the immediate need to verify the contractual requirements and may lead to unnecessary actions without confirming the project's commitments.