Project Management Professional (PMP) — Question 907
A project's business case was just approved and the project manager is creating the benefits management plan. It is unclear how the benefits from the project align with the organization's vision.
What should the project manager do first to verify alignment?
Answer options
- A. Consult with the project team members to gain their opinions.
- B. Ask the project team to delay the kick-off while resolving the concern.
- C. Meet with the project sponsor to obtain more information.
- D. Request a copy of the project assumptions log for more insight.
Correct answer: C
Explanation
Meeting with the project sponsor is crucial as they can provide insights into the organization's vision and how the project's benefits align with it. Consulting the project team may yield opinions but won't clarify the organizational alignment. Delaying the project kick-off may not be necessary, and the assumptions log may not directly address the alignment concern.