Project Management Professional (PMP) — Question 906

A company's project management office (PMO) has started to implement iterative tools. The project manager is starting a new project and has identified an opportunity to use the new tools. There is disagreement among stakeholders about the use of the adaptive tool.

What should the project manager do first?

Answer options

Correct answer: D

Explanation

The correct answer is D because understanding the reasons for disagreement helps identify the specific concerns of stakeholders and facilitates finding a consensus. Options A and B do not address the root cause of the disagreement, while option C may overlook the importance of first understanding the stakeholders' perspectives.