Project Management Professional (PMP) — Question 909
An intern is replacing a critical resource midway through a sprint. To help the intern get up to speed, the project manager assigns a senior engineer in the team as the intern's mentor. Two months later, the project goes into critical status, delaying the release milestone by a month.
What should the project manager have done to avoid this scenario?
Answer options
- A. Requested an experienced resource as a replacement
- B. Negotiated additional time to complete the project
- C. Allocated additional time for mentoring
- D. Convinced the critical resource to remain on the project
Correct answer: A
Explanation
The correct answer is A because having a more experienced resource would ensure a smoother transition and reduce the risk of delays. Options B and C do not address the immediate need for expertise, while D may not be feasible if the critical resource is already committed elsewhere.