Project Management Professional (PMP) — Question 909

An intern is replacing a critical resource midway through a sprint. To help the intern get up to speed, the project manager assigns a senior engineer in the team as the intern's mentor. Two months later, the project goes into critical status, delaying the release milestone by a month.

What should the project manager have done to avoid this scenario?

Answer options

Correct answer: A

Explanation

The correct answer is A because having a more experienced resource would ensure a smoother transition and reduce the risk of delays. Options B and C do not address the immediate need for expertise, while D may not be feasible if the critical resource is already committed elsewhere.