Project Management Professional (PMP) — Question 895
A construction project for a nuclear power plant will reduce the region's energy dependence on external electricity supplies. The project manager has received support for the project from several leaders in the region. However, some people from the government want to stop this project to focus on developing renewable energy sources.
Which stakeholders should the project manager include in the stakeholder engagement plan?
Answer options
- A. Stakeholders who disagree with the project so as to proactively manage their expectations.
- B. Stakeholders who have been identified and who have needs and a potential impact on the project.
- C. Stakeholders who are supporting the project in order to obtain additional resources.
- D. Stakeholders who are selected by the project sponsor who have a potential impact on the project.
Correct answer: B
Explanation
The correct answer is B, as it emphasizes the importance of involving stakeholders who have been identified as having needs and the ability to impact the project, ensuring a comprehensive engagement strategy. Option A, while important, focuses solely on managing opposition rather than a broader stakeholder approach. Option C limits engagement to supporters, which could overlook critical perspectives, and option D, while relevant, does not prioritize the needs and influence of all identified stakeholders.