Project Management Professional (PMP) — Question 894
A project defined to be executed in four months is divided into eight iterations. During its first retrospective, the team realizes that only one member has experience doing a key project requirement.
What should the project manager do?
Answer options
- A. Invite the team member to share experience in the next retrospective.
- B. Ask the sponsor to add team members with the required experience.
- C. Plan knowledge-sharing sessions within the team.
- D. Ask the sponsor for a training course for the team.
Correct answer: C
Explanation
The correct answer is C because planning knowledge-sharing sessions allows the entire team to benefit from the expertise of the experienced member, fostering collaboration and learning. Option A is less effective as it limits the sharing to one meeting. Option B may not be feasible due to resource constraints, and option D doesn't directly address the immediate need for knowledge sharing among the current team members.