Project Management Professional (PMP) — Question 893
During a project kickoff meeting, the client indicates that the benefits of the project will become the most important revenue stream for the company. The client needs to find opportunities to deliver value to their company as soon as possible.
What should the project manager do?
Answer options
- A. Apply project schedule compression techniques to deliver benefits faster.
- B. Plan project iterations taking into consideration value delivery.
- C. Develop a project management plan to achieve the goals of the project faster.
- D. Align the goals of the project with the revenue goals of the company.
Correct answer: B
Explanation
The correct answer is B because planning project iterations with a focus on value delivery allows the team to prioritize tasks that provide the most benefit to the client quickly. While A suggests speeding up the timeline, it does not ensure that the delivered features are valuable. C focuses on speed but lacks the emphasis on value delivery, and D, while important, does not address the immediate need for quick value generation.