Project Management Professional (PMP) — Question 893

During a project kickoff meeting, the client indicates that the benefits of the project will become the most important revenue stream for the company. The client needs to find opportunities to deliver value to their company as soon as possible.

What should the project manager do?

Answer options

Correct answer: B

Explanation

The correct answer is B because planning project iterations with a focus on value delivery allows the team to prioritize tasks that provide the most benefit to the client quickly. While A suggests speeding up the timeline, it does not ensure that the delivered features are valuable. C focuses on speed but lacks the emphasis on value delivery, and D, while important, does not address the immediate need for quick value generation.