Project Management Professional (PMP) — Question 896
A project sponsor has requested a trend analysis of all risks that the project has monitored over the past 12 months. What should the agile project manager do?
Answer options
- A. Extract this from the project risk register tracking tool and issues log
- B. Refer the sponsor to the contract document
- C. Organize a stakeholder meeting to brainstorm on general project risks
- D. Share the annual report with the sponsor
Correct answer: A
Explanation
The correct answer is A because extracting information from the project risk register tracking tool and issues log provides the specific data needed for the trend analysis. Option B is not appropriate since the contract document may not contain relevant risk information. Option C would not yield the required historical data, and Option D does not specifically address the request for trend analysis over the past 12 months.