Project Management Professional (PMP) — Question 880

An agile project team received an assignment to develop an industrial system that interfaces with robots. The project team does not have any previous experience performing this type of work. Team members are interested in acquiring such expertise but it may result in a project delay.

How should this situation be handled?

Answer options

Correct answer: B

Explanation

Option B is correct because adding an experienced professional fosters knowledge transfer within the team, enhancing their skills for future tasks. Options A and D rely on external help, which may not build internal capabilities, while option C could lead to fragmentation and inefficiencies in teamwork.