Project Management Professional (PMP) — Question 879
Due to a change in market conditions, the business value for the original project requirements has changed. What should the project manager consider for execution?
Answer options
- A. Evaluate and work on small requirements to deliver business value.
- B. Negotiate with the stakeholder to deliver with existing business value.
- C. Continue as planned since changes will have no impact on the project.
- D. Take into consideration the requirements with the modified business value.
Correct answer: D
Explanation
The correct answer is D because the project manager needs to consider the new business value to ensure the project remains relevant and valuable. Option A, while focusing on small requirements, does not address the changed value comprehensively. Option B ignores the necessity of adapting to new market conditions, and option C is incorrect as it assumes that changes will not affect the project, which is unlikely.