Project Management Professional (PMP) — Question 873

A project manager acquired information from the market that would reduce the business value being delivered by an ongoing project. Based on that information, the project manager believes the project should be stopped.

How should the project manager handle the situation?

Answer options

Correct answer: D

Explanation

The correct answer is D because it emphasizes the need to engage with the project sponsor to evaluate the project's business value based on new market information, which is a responsible approach before making drastic decisions. Option A jumps to canceling the project without thorough analysis, option B focuses on backlog adjustments without addressing the core issue, and option C ignores the new information entirely by continuing as planned.