Project Management Professional (PMP) — Question 872

An iteration is almost finished, but the team is struggling to complete the stories that require more time. What should the project manager do first?

Answer options

Correct answer: A

Explanation

The correct answer is A because meeting with the project team allows for a collaborative approach to identify the root cause of the delays and develop a resolution. Options B and C may not address the immediate problem effectively, while D would only update documentation without solving the underlying issue.