Project Management Professional (PMP) — Question 871

A project team is working to deliver a solution to manage nationwide crisis relief operations. The project team is spending most of its time in meetings with end users. The meetings have been slowing down project progress.

What should the project manager do to keep the deployment on track while obtaining stakeholder approval?

Answer options

Correct answer: D

Explanation

The correct answer, D, allows the project team to maintain transparency and keep stakeholders informed while minimizing the number of meetings. This approach helps in managing communication effectively without impeding project progress. Options A, B, and C either do not address stakeholder engagement adequately or risk rushing development without proper input.