Project Management Professional (PMP) — Question 874
One of the key stakeholders on the project team reaches out with an additional requirement that may impact the overall schedule. A discussion with another stakeholder suggests that this might just be a small task.
What should the project manager do?
Answer options
- A. Perform a qualitative risk analysis.
- B. Coordinate design document preparation.
- C. Request further clarification of the requirement.
- D. Manage the engagement of this stakeholder.
Correct answer: C
Explanation
The correct approach is to seek additional clarification regarding the requirement, as understanding the specifics will help assess its impact on the schedule. Performing a qualitative risk analysis may be premature without clear details, while coordinating design documents or managing stakeholder engagement does not address the immediate need for clarification.