Project Management Professional (PMP) — Question 862
A project manager is assigned to an analysis project for a customer. The project manager needs to keep the performance of the team a step ahead of the estimated delivery schedules.
What should the project manager do to impact the sprint cycles going forward on the project?
Answer options
- A. Build the capacity of the team to improve sprint cycles and provide weekly trend reports.
- B. Engage an expert in project management to explain to the team how fast to work on the sprint cycle.
- C. Work with the team on how to focus on only precommunicated project results.
- D. Train the team to analyze data and complete the user stories within the schedule.
Correct answer: A
Explanation
The correct answer, A, focuses on building the team's capacity, which is essential for improving sprint cycles and tracking progress through reports. Option B suggests bringing in an expert, which may not directly enhance the team's capabilities. Option C limits the team's focus to precommunicated results, potentially stifling innovation and improvement. Option D, while beneficial for user story completion, does not address the overall improvement of sprint cycles.