Project Management Professional (PMP) — Question 861

A new project manager is assigned to an ongoing agile innovation project that started 2 weeks ago. After reviewing the project, the new project manager discovered that the previous project manager was planning to use a predictive approach. The previous project manager planned to present the first major deliverable to the client when the project was completely finished in 8 months.

What should the new project manager do?

Answer options

Correct answer: D

Explanation

The correct answer is D because agile methodologies emphasize delivering incremental value to the client through small, iterative releases. Options A and B maintain a predictive approach, which contradicts agile principles, while option C does not address the need for agile delivery and simply shifts the timeline.