Project Management Professional (PMP) — Question 863
An organization is using a hybrid delivery approach for a complex project. In the iteration review, a senior manager asks for a complete redesign of the functionality presented. The manager is new to the organization and has no experience with agile delivery.
What should the project lead do first?
Answer options
- A. Ask the development team to explain how the functionality was implemented.
- B. Ask the manager for more details about their expectations for the functionality.
- C. Inform the manager that the agreed upon scope cannot be changed.
- D. Inform the manager that their request will be escalated to the project sponsor.
Correct answer: B
Explanation
The correct answer is B because understanding the manager's expectations is crucial before making any decisions about redesigning the functionality. Options A, C, and D do not prioritize clarifying the manager's intent, which is essential for effective communication and project alignment.