Project Management Professional (PMP) — Question 836

A project for developing software for a retail company's procurement system is in the initiation phase. The project sponsor has expressed concern that the forecasted project implementation date coincides with the company's financial budget planning period.

Which two actions should the project manager take next to address this concern? (Choose two.)

Answer options

Correct answer: B, C

Explanation

The correct actions are B and C because facilitating a risk workshop allows for a comprehensive identification and assessment of risks, while logging the concern as a risk enables the project manager to evaluate its impact systematically. Option A is incorrect as it does not address the concern, D is inappropriate because changing the date without assessment may not resolve the underlying issue, and E is misleading since it dismisses the sponsor's valid concern.