Project Management Professional (PMP) — Question 837
In a complex development project with many clients and team members, there have been delays in completing the required work. What should the project manager do?
Answer options
- A. Empower the team members to do their work.
- B. Work with the team to develop a risk response plan.
- C. Send an email to human resources (HR) about this situation.
- D. Inform the project sponsor about this situation.
Correct answer: B
Explanation
The correct answer is B because developing a risk response plan helps address the underlying issues causing the delays. Option A, while empowering, does not directly tackle the delays. Option C is not proactive in resolving the issue, and option D, while informative, does not address the root cause of the delays.