Project Management Professional (PMP) — Question 835

A project team is executing a project to replace an existing system with a new one. A new project manager has been hired and observes that the team consist of professionals who have worked with the older system, and others who have little previous experience.

What should the project manager do to ensure project success?

Answer options

Correct answer: A

Explanation

The correct answer is A because evaluating the team's effectiveness and identifying development needs allows the project manager to address skill gaps and improve overall performance. Option B is incorrect as it may not consider the current capabilities of team members, while C, although beneficial, does not provide a structured approach to enhancing team effectiveness. Option D, while useful, does not directly empower the project manager to lead the team effectively.