Project Management Professional (PMP) — Question 802

A project manager is leading a digital transformation project in a large geographically distributed organization. During the execution phase, the project team noticed that the organization's employees and heads of departments have different perceptions and expectations of the project and its outcome. The project manager is afraid that it may impact the project's success.

Which two actions can the project manager do to resolve this issue? (Choose two.)

Answer options

Correct answer: A, C

Explanation

The correct answers, A and C, focus on enhancing communication and ensuring that all stakeholders clearly understand the project objectives. Engaging stakeholders helps bridge perception gaps, while sharing objectives ensures alignment. Options B and D, while potentially helpful, do not address the broader communication needs effectively, and option E is dismissive of the issue, risking project success.