Project Management Professional (PMP) — Question 801

Three testers joined the project team just before the end of the build. During the project team meeting, the testers indicated that the project quality is poor, and they should not continue testing until all the defects are fixed.

Which three actions should the project manager do? (Choose three.)

Answer options

Correct answer: B, C, D

Explanation

The correct actions involve gathering more information from the testers (B), facilitating a discussion with the project team to address the quality concerns (C), and adhering to the testing plan to ensure project progress (D). Stopping the project (A) is not practical at this stage, and asking for sponsor assistance (E) may not be necessary until more information is gathered.