Three testers joined the project team just before the end of the build. During the project team meeting, the testers indicated that the project quality is poor, and they should not continue testing until all the defects are fixed.
Which three actions should the project manager do? (Choose three.)
Answer options
- A. Stop the project and review the output.
- B. Ask the testers to provide additional information.
- C. Brainstorm the issue with the project team.
- D. Continue with testing according to the plan.
- E. Ask the sponsor for assistance and guidance.
Correct answer: B, C, D
Explanation
The correct actions involve gathering more information from the testers (B), facilitating a discussion with the project team to address the quality concerns (C), and adhering to the testing plan to ensure project progress (D). Stopping the project (A) is not practical at this stage, and asking for sponsor assistance (E) may not be necessary until more information is gathered.