Project Management Professional (PMP) — Question 800

A project manager who is providing development support for a product notices some of their long-standing customers moving to a competitor because of improved value being delivered from their product. What should the project manager do first?

Answer options

Correct answer: A

Explanation

The correct answer is A because the project manager needs to first understand if there has been any change in the product's value delivery before taking further actions. Options B and D are premature as they assume changes need to be made without confirming the current situation, while C suggests halting development, which may not be necessary at this stage.